Управление структурой комплектов машин при строительстве земляного полотна на переходящих объектах
Abstract
The article describes the method of management staff of specialized sets of road cars to excavate the construction of roads of considerable length (50 km or more) in a difficult environment for a number of years. The distribution volume of work on the rolling facility in accordance with the calendar in the project construction organization predicts an operating time of machines involved, their technical and economic indicators in each year of construction. The proposed model provides a rational adjustment of sets of machines and compositions in accordance with the predicted performance to make changes in the fleet structure in the production of works projects.