VERTICAL LINEAR PROJECT SCHEDULING FOR HIGH-RISE BUILDINGS
Abstract
In this paper, an application to high-rise buildings of VPM (Vertical Production Method) and an example will be given which is composition of two distinct and preferable methods are CPM (Critical Path Method) that is prefering against traditional Bar-Charts or schedules especially in big and costly investments and LOB (Line of Balance) technique that is suitable for using in linear project planning. Thus, it could be expected that to show the way of the method to designer and manufacturer about subjects which are activity, priority and sequencing of high-rise project, speeds of activity and construction, completion times, to add or take out some terms to schedule at the state of project changing.