Media Komunikasi Teknik Sipil (Feb 2024)

Analysis of Steel Beam Installation Operation Productivity (Case Study: Construction of University Pasundan Campus II)

  • Yongki Alexander Tanne,
  • Andhyka Putra Pratama,
  • Reza Rahardian

DOI
https://doi.org/10.14710/mkts.v29i2.54764
Journal volume & issue
Vol. 29, no. 2
pp. 233 – 242

Abstract

Read online

Construction operations productivity remains a challenge due to the influence of space limitations and construction methods. This condition was experienced by the construction of Pasundan University’s new campus building within a narrow and congested location. This research carried out a productivity evaluation on the steel beam installation based on Time Studies, MPDM, Work Sampling and 5-Minutes Rating. Productivity analysis uses the MPDM, Cycle Chart, Process and Crew Balance Chart. The evaluation of the overall productivity of steel beam installation operations shows a comparison of the percentage of work execution versus delay of 62% versus 38%. This result is quite good considering that the proportion of construction worker productivity is in the range of 40-70% compared to 62% on this project. Improvement of productivity can still be done by preventing delays due to equipment; efficiency of the number of workers; as well as optimizing the duration of each task by referring to the best cycle duration. Thus, the productivity can increase from 10.36 minutes/unit to 6.25 minutes/unit. It is hoped that these results will attract similar research with objects to produce productivity data on construction operations in Indonesia and encourage an improvement in the construction sector.

Keywords