Physical Review Accelerators and Beams (Dec 2020)

High intensity operation using proton stacking in the Fermilab Recycler to deliver 700 kW of 120 GeV proton beam

  • Robert Ainsworth,
  • Philip Adamson,
  • Bruce C. Brown,
  • David Capista,
  • Kyle Hazelwood,
  • Ioanis Kourbanis,
  • Denton K Morris,
  • Meiqin Xiao,
  • Ming-Jen Yang

DOI
https://doi.org/10.1103/PhysRevAccelBeams.23.121002
Journal volume & issue
Vol. 23, no. 12
p. 121002

Abstract

Read online Read online

As part of the NOvA upgrades in 2012, the Recycler was repurposed as a proton stacker for the Main Injector with the aim to deliver 700 kW. Since January 2017, this design power has been run routinely. The steps taken to commission the Recycler and run at 700 kW operationally will be discussed. Major improvements include a new collimation system to control transverse losses and diode damper system to damp the resistive wall instability during slip-stacking. Plans for future running will also be discussed.