Investigation of the influence of flooded bench hydraulic mining parameters on sludge pond formation in the pit residual space

  • Sobko Borys,
  • Lozhnikov Oleksii,
  • Drebenshtedt Carsten

DOI
https://doi.org/10.1051/e3sconf/202016800037
Journal volume & issue
Vol. 168
p. 00037

Abstract

Read online

The research aim is establishment of effective parameters for mining of flooded bench by a hydro-mechanized complex with dumping of enclosing rocks in a sludge pond of pit residual space. The established research results make it possible to choose the effective width of the dredger mining cut at the hydromechanical method, taking into account the volume of the excavation and dump pipeline movements. Two technological schemes for the formation of a sludge pond in the pit residual space are proposed, they differ in the direction of the sludge pond movement relatively to the pit front. The established dependence of the number of movements of the sludge pond pipeline on the width of the dump pass allows to choose its effective value, taking into account the number of discharge pipes. Based on the dependence of the average monthly excavation volume and the number of movements of sludge pond pipeline on the width of cut face, the optimal number of discharge pipes is established. The research results allow establishing the effective dredger width of the sludge pond and the number of discharge pipes provided that a transverse or longitudinal pass at the internal sludge pond formation is applied during the mining.