DETERMINATION OF ENGINEERING CRITERIA OF DELICE (ANKARA) BRIDGE BY CPM METHOD

  • M. Haluk ÇELİK,
  • Recep KANIT,
  • Gamze ERDİLLER,
  • Metin ERDAMAR

Journal volume & issue
Vol. 1, no. 2
pp. 95 – 103

Abstract

Read online

In this study, CPM-PERT method is used to find out the minimum time and cost of the bridge constructed in Delice (Ankara) on the Koru river. The reinforced concrete bridge has a 13.70 m support distance and an 8 m platform witdh. In the method; planning, management and cost prices in Early Finish and Late Finish times were taken into account.