E3S Web of Conferences (Jan 2019)

Research on Construction Practice of Assembled Substation——A Case in Anhui Xuancheng Xinhang 110kV Substation Project

  • Ximing Chen,
  • Dian Bao,
  • Chaojun Qian,
  • Shao-jie Zhang

DOI
https://doi.org/10.1051/e3sconf/201913602038
Journal volume & issue
Vol. 136
p. 02038

Abstract

Read online

The assembled substation is a substation construction that is "resource-saving, environment-friendly, and industrialized" through prefabrication and on-site installation. Taking the Xuancheng Xinhang 110kV substation project in Anhui as an example, this paper studies the standardization development of assembled industrial buildings and substations at home and abroad, points out the problems existing in the construction and buildingpractice of the assembled substation, and puts forward relevant suggestions for these problems.