Read online

The paper includes selected aspects of the study, whose goal is to hold the historical crane 642-24 in its current location after the modification of trestle bridge static scheme. The scope of the paper includes the assessment of current technical condition of the object, a presentation of FEM analyses, a description of the assumed load cases, results of the static calculations, checking the effort of construction elements, global and local structure stability and its dynamic characteristics.