REPNET: project scheduling and workflow optimization for Construction Projects
Abstract
Project planning and control are core processes for construction management. In practice project planning is achieved by network - based techniques like Precedence Diagramming Method (PDM).Indeed many researchers and practitioners claims that networking techniques as such do not provide a suitable model for construction projects. Construction process modeling should incorporate for specific features of resource flows through project activities. So an improved resource scheduling method for construction is developed, called REPNET, based on a precedence network plotted on a resource–space chart and presented with a flow-line chart. The heuristics of REPNET are used to carry out resource timing while optimizing processes flows and resource usage. The method has been tested on a sample project.