Buildings (Feb 2024)

Exploring Cost Variability and Risk Management Optimization in Natural Disaster Prevention Projects

  • Jin-Ho Cho,
  • Young-Su Shin,
  • Jae-June Kim,
  • Byung-Soo Kim

DOI
https://doi.org/10.3390/buildings14020391
Journal volume & issue
Vol. 14, no. 2
p. 391

Abstract

Read online

The purpose of this study is to analyze the causes of cost variation in natural disaster prevention projects (NDPPs) in Gyeongsangbuk-do, South Korea, and develop tailored cost and risk management strategies. Utilizing a binary logistic regression model, this research uniquely focuses on the Gyeongsangbuk-do region, gathering data from 244 stakeholders through an online survey. The study identifies critical variables influencing cost deviation, including project management risk (PMR), project costing and execution risk (PCER), project execution strategy risk (PESR), construction project risk (CPR), project cost and schedule risk (PCSR), project management challenges (PMCs), and construction project subcontractor and safety management (CPSSM). Significant findings revealed PMR (OR = 3.744, 95% C.I. [1.657, 8.457]), PCER (OR = 5.068, 95% C.I. [2.236, 11.484]), and PESR (OR = 3.447, 95% C.I. [1.853, 6.413]) as the primary causes of cost deviation, alongside the notable impacts of other factors such as CPSSM. The developed predictive model is instrumental for NDPP stakeholders in Gyeongsangbuk-do, providing advanced risk management capabilities and aiding in effective preventive measures. This study not only corroborates theoretical hypotheses from previous research but also offers new insights into cost deviation causes in NDPPs, thereby enhancing strategic decision-making and advancing risk management perspectives.

Keywords