E3S Web of Conferences (Jan 2017)
Shortening start-up and an extension of the power unit load range
Abstract
A power plant with additional water pressure tanks was proposed. The maximum rise in the block electric power resulting from the shut-off of low-pressure regenerative heaters was determined. At that time, the boiler is fed with hot water from water pressure tanks acting as heat accumulators. Accumulation of hot water in water tanks is also proposed in the periods of the power unit small load. In order to lower the plant electric power in the off-peak night hours, water heated to the nominal temperature in low-pressure regenerative heaters is directed from the feed water tank to pressure tanks. The water accumulated during the night is used to feed the boiler during the period of peak demand for electricity. Pressure accumulators are proposed to be used for the rapid start-up of the boiler from a cold state. The evaporator of the boiler is filled at the beginning of start-up with hot water from the accumulators. Drops in the power block electric power were determined for different capacities of the tanks and periods when they are charged. The tanks may also be used to ensure a sudden increase in the electric power of the unit that is operating in the automatic system of frequency and power control (in Polish: ARCM).