IEEE Access (Jan 2020)

Crashing Construction Project Schedules by Relocating Resources

  • Michal Tomczak,
  • Piotr Jaskowski

DOI
https://doi.org/10.1109/ACCESS.2020.3044645
Journal volume & issue
Vol. 8
pp. 224522 – 224531

Abstract

Read online

A variety of schedule compression techniques are used to get delayed construction projects “back on tracks”. This paper presents a new optimization approach to schedule crashing by relocating some of the workers from non-critical to critical processes (changing composition of crews using the initial pool of workers) and employing additional resources. The authors describe their idea in the form of a mixed-integer linear problem. A numerical example illustrates the merits of the proposed approach. The method may become a practical support in construction scheduling decisions.