Energies (Sep 2021)

Hydrogen Infrastructure Project Risks in The Netherlands

  • Pieter W. M. Vasbinder,
  • Antoine W. G. de Vries,
  • Wim Westerman

DOI
https://doi.org/10.3390/en14196009
Journal volume & issue
Vol. 14, no. 19
p. 6009

Abstract

Read online

This study aims to assess the potential risks of setting up a hydrogen infrastructure in the Netherlands. An integrated risk assessment framework, capable of analyzing projects, identifying risks and comparing projects, is used to identify and analyze the main risks in the upcoming Dutch hydrogen infrastructure project. A time multiplier is added to the framework to develop parameters. The impact of the different risk categories provided by the integrated framework is calculated using the discounted cash flow (DCF) model. Despite resource risks having the highest impact, scope risks are shown to be the most prominent in the hydrogen infrastructure project. To present the DCF model results, a risk assessment matrix is constructed. Compared to the conventional Risk Assessment Matrix (RAM) used to present project risks, this matrix presents additional information in terms of the internal rate of return and risk specifics.

Keywords