Mining and Metallurgy Engineering Bor (Jan 2013)

Transient time determination at start up of belt conveyor for ore T.109

  • Rajković Branislav,
  • Ilić Zoran,
  • Mijović Radomir

DOI
https://doi.org/10.5937/mmeb1302053R
Journal volume & issue
Vol. 2013, no. 2
pp. 53 – 60

Abstract

Read online

This work gives the method of transient time determination of the belt conveyor in the case of its start up in the example of a belt conveyor for ore at the open pit 'Veliki Krivelj" with capacity of 2000 t/h. The analysis was made by calculation procedure and it represents a universal calculation method of conveyor belts whose results are indispensable for verification the reliable operation of selected electric motors during the start up of belt conveyor. Also, technical characteristics of all components of drive units are given as well as their layout.